Skip to content

Be prepared for storm season. Safety tips and videos

Electrical connection requests

To add electrical service to a location that doesn't have an electrical connection yet, you'll need to request an electrical connection.

We offer two main types of electrical connection services. Depending on your project complexity, you'll need to apply for either an express connection or a design connection. Find out more below.

On this page:

If you're moving to an address that has an electrical connection, go immediately to start, stop or move your service.

Before you begin

Before requesting an electrical connection, start by discussing yours electrical needs with an electrician, electrical consultant, or developer who's experienced with the process. It's important to have a professional guide you at this stage.

The technical requirements of your project will determine whether it's considered an express connection or a design connection. These include:

  • The distance between your project location and the existing BC Hydro infrastructure that supplies electricity.
  • The amount of electricity you need.
  • Whether there's sufficient electricity to support your needs.

An express connection is:

  • A connection that doesn't require addition or modification to the distribution system to provide the service.
  • The quickest way to get an electrical connection installed.
  • A connection that can be completed for a standard charge and fee.

A design connection is:

  • A more complex, multi-phase electrical design project that requires our design team's technical expertise to design, plan and implement.
  • A project that includes installing, replacing, or moving our infrastructure including power lines, poles, transformers, service boxes or fuses to help you get connected.
  • A project that may require an extension fee to install the infrastructure.

Please work with your electrician, electrical consultant or developer to answer the following questions. If you answer "yes" to one or more of the questions below, you should likely proceed with an express connection request.

Otherwise, your request should likely be handled as a design connection project instead.

Service location

  • Overhead: Is your service location within 30 metres from an existing BC Hydro pole?
  • Underground: Is there existing underground BC Hydro infrastructure (service box or transformer) near your property? 
  • Will the meter be located on the exterior of the structure or connection point? (Not in a meter room)

Service size

  • Does your request require an electrical connection that is 200 Amps or less?
  • Does your request require either a single-phase 120/240 V or 120/208 V?

Select a connection type

Select a connection type to see the associated process, timeline, costs and more.

Manage your requests

Electrical connection requests are handled online through MyHydro, available on desktop and mobile devices. If you don't have a MyHydro profile yet, create one first.

Log in to submit requests, check project status, share documents and more.

Start a request     Manage existing requests

For guidance, see how to manage a project using MyHydro [PDF, 828 KB].

Glossary

Every BC Hydro pole has a tag with an identification number. A pole tag could have a seven-digit or 14-digit identification number. To read a 14-digit identification number, use the first eight numbers from the top row (starting from the left) and the first six numbers from the bottom row (starting from the left).

Pole tag 7 digit
Pole tag 14 digit

Equipment that converts electrical energy from one voltage, through electrical induction, to another voltage. Generally, we use step-down transformers to convert our distribution system voltage to levels that can be safely used in homes and buildings.

Example of overhead single-phase transformer
Overhead single-phase transformer
Example of three-phase pad-mounted transformer
Three-phase pad-mounted transformer
Example of overhead three-phase transformer
Overhead three-phase transformer
Example of three-phase pad-mounted transformer
Single-phase low-profile transformer

Power lines that carry the high voltage of our distribution system after it leaves the substation. Larger services may connect directly to our primary distribution lines for service.

Power lines that connect commercial and residential customers to our system after a transformer lowers the voltage from our primary distribution line.

A non-energized tensioned cable with a yellow guard attached to a pole and anchored into the ground.

A room in a building housing electrical equipment, such as meters. Rooms containing BC Hydro's equipment have access provisions and technical requirements you'll need to incorporate into your project.

Meter or electrical room
Meter or electrical room

Commonly provided in residences and retail commercial buildings. The standard single-phase voltages provided by us are 120/240 V and 120/208 V.

Typically provided to larger commercial and industrial customers since large motors and other large loads operate more efficiently with three-phase power. The standard three-phase power voltages provided by us are 347/600 V and 120/208 V.

The combined voltage and amperage of your request. Larger services have greater impacts on our system and may have increased requirements and costs.

Connects your electrical system to our secondary distribution system, most often at poles, transformers or service boxes.

Electrical equipment installed on or between poles, including overhead transformers, switches, regulators, capacitors, conductors and guy wires. Many of our poles are jointly owned with TELUS and also have communication cables attached below BC Hydro's electrical equipment.

Electrical equipment installed underground or at ground level. Includes underground cables, junction boxes, service boxes, low profile transformer, pad-mounted transformers, chambers and vaults.

In the case of a work with, both the BC Hydro crew and the electrical contractor are required to be on site at the same time in order to complete work. A one-trip work with requires that the crew attend site alongside the electrician just one time. In a two-trip work with, the crew disconnects electrical power in the morning and reconnects later the same day. This allows the electrician to complete work while the area is de-energized.