To give you an idea of the work and potential costs involved, here are two recent projects involving switchgear in B.C. To protect customer privacy, we’ve removed the customers’ names and locations of their projects.
Please note: Requirements are determined by engineering on a case-by-case basis. As the reasons and conditions in the examples below are not directly transferable from one project to another, customers must engage early with BC Hydro to confirm switchgear requirements and get project-specific guidance. Costs to the customer will vary considerably depending on project scope and complexity.
A food processor's growth: Vista switchgear, three-phase power line
A new food processing plant was proposed for Surrey that would eventually require 7.5 megawatts of power. The customer required energization as soon as possible, and switchgear was required to coordinate the customer’s electrical protection with BC Hydro’s protection. BC Hydro also upgraded a section of overhead power line servicing from single-phase to three-phase to accommodate future power demands, system capacity and reliability.
While we prefer to install switchgear on public property, the municipality is among many in B.C. that requires that it was installations on the customer's property. We installed above-ground Vista switchgear on customer property, with the customer paying for civil works related to installation of the switchgear and a low-voltage control box. We also needed space to install a single-phase pad mount transformer power supply.
The total project cost to upgrade electrical service to the plant was about $660,000 (including costs for design, system improvement, extension, service connections, switchgear, civil construction, right of way, and metering). With BC Hydro’s revenue contributions – which reflect the updated distribution extension policy – the end cost to the customer was about $54,000 for the upgrade including switchgear.
Mid-rise apartment: switchgear, undergrounding of power lines
The owner of a planned mid-rise 371-unit apartment building in Richmond requested that BC Hydro supply an electrical demand of 3.3 megawatts. The customer also requested that existing overhead power lines in an adjacent laneway be replaced with underground lines.
To meet system and customer needs, the project also required above-ground automated switchgear on the customer’s property.
BC Hydro work included removal of 10 spans of three-phase overhead feeder lines and installation of 270 metres of underground distribution cable in their place. Installation of the switchgear required construction of a low-voltage enclosure) along with the addition of a single-phase pad mount transformer.
The total cost of the project was about $2.66 million, including extension fee, right of way and metering, civil works related to the switchgear installation, and other construction. Following BC Hydro's revenue contributions and updated distribution extension policy, the customer paid about $56,000 for the service connection including switchgear.