Competitive electricity acquisition processes (CEAP)

If we decide to run a competitive process to acquire electricity, we'll formally initiate a competitive electricity acquisition process (CEAP). This is most commonly initiated to support a call for power.

Participants who want to participate will have the option to attend workshops to learn about the process and requirements. If you choose to take part in the CEAP, you'll need to:

  • Submit the required interconnection documents according to the provided timeline.
  • Pay the applicable deposits as required in the OATT's Attachment M-2 [PDF, 135 KB].

 

Current CEAP: 2025 Call for Power CEAP

This CEAP is to support the 2025 Call for Power.

In preparation for this process, we hosted two CEAP workshops.

 

Key dates

Activity Timing

BC Hydro begins accepting pre-submission of
CEAP Interconnection Requests (IRs) and optional CEAP enrollment sign-up opens

July 16, 2025 

Optional CEAP enrollment sign-up closes

August 11, 2025

Deadline for pre-submission of CEAP IRs

September 2, 2025 at 5 p.m.
Pacific time

Submission of CEAP IRs

October 2, 2025 at 5 p.m.
Pacific time

Feasibility study report delivered

November 19, 2025

Selection of successful participants

Early 2026



Submission instructions

The pre-submission window for the 2025 Call for Power CEAP closed on September 2, 2025 at 5 p.m. Pacific Time. Participants who did not make a pre-submission are not eligible for this CEAP. 

Supporting information

Have questions?

For 2025 Call for Power CEAP please email CEAP2025@bchydro.com. We are limited in the degree to which we can share information that could impact or improve project outcomes due to our commitment to fairness.

For all other Call for Power RFP questions please see the Questions and answers for the 2025 Call for Power.

 

Past CEAPs

2024 Call for Power CEAP

The 2024 Call for Power CEAP has been concluded. All proponents were notified in December 2024 of the result of the CEAP.